
Mount Maunganui
All Maintenance Updates by Fulton Hogan in the Mount Maunganui Area
What’s happening in the Mount?
Tauranga City Council has contracted Fulton Hogan Ltd to carry out repairs and maintenance in Mount Maunganui.
This work is part of the Council’s annual programme, improving road safety and investing in our roading assets, including footpaths.
Our work is very weather dependant so dates may change due to the weather or other unforeseen circumstances.
Our roadworks include heavy machinery which unfortunately can create noise, vibration and types of environmental factors (including cement dust for example).
VALLEY ROAD Footpath Repair
Status: COMPLETED
Date of Works: MONDAY 15TH SEPTEMBER 2025
Type of Works: FOOTPATH REPAIR
Pedestrians will be shown the safest path to follow at all times. We will endeavour to keep noise to a minimum where possible.
Additional Info
The area highlighted in BLUE indicates the work zone. The footpath will be closed, however there will be a Stop/Go at McDowell Street for plant movement.
During the curing process, it’s essential that no traffic passes over the freshly poured concrete. The footpath will open again on Friday 19th September 2025.
PURIRI STREET AND TAWA STREET INTERSECTION Preseal Repairs - Cement Stabilising
Status: COMPLETED
Date of Works: TUESDAY 16TH AND WEDNESDAY 17TH SEPTEMBER 2025
Type of Works: Preseal Repairs - Cement Stabilising
The road surface is at the end of its life cycle and needs resurfacing to keep it watertight and prevent further deterioration. Preseal repairs are done first, and we then return later in the season to resurface the entire stretch of road with chipseal.
For cement stabilising we rotary hoe the underlying pavement layer with cement to strengthen it. This new pavement is then trimmed, shaped and compacted. We will also seal these patches. We will notify you with another letter drop when we come back to resurface the road with chipseal.
Additional Info
The affected area is highlighted BLUE. The site will be operating under Stop/Go Traffic Management.
Residents will still be able to access their properties if required. Please ask our traffic management team and allow them time to arrange access.
RITA STREET Preseal Repairs - Cement Stabilising
Status: COMPLETED
Date of Works: TUESDAY 16TH AND WEDNESDAY 17TH SEPTEMBER 2025
Type of Works: Preseal Repairs - Cement Stabilising
The road surface is at the end of its life cycle and needs resurfacing to keep it watertight and prevent further deterioration. Preseal repairs are done first, and we then return later in the season to resurface the entire stretch of road with chipseal.
For cement stabilising we rotary hoe the underlying pavement layer with cement to strengthen it. This new pavement is then trimmed, shaped and compacted. We will also seal these patches. We will notify you with another letter drop when we come back to resurface the road with chipseal.
Additional Info
The affected area is highlighted BLUE. The site will be operating under Stop/Go Traffic Management.
Residents will still be able to access their properties if required. Please ask our traffic management team and allow them time to arrange access.
MARU STREET Footpath Repair
Status: ACTIVE
Date of Works: WEDNESDAY 17TH TO THURSDAY 18TH SEPTEMBER 2025
Type of Works: FOOTPATH REPAIR
Pedestrians will be shown the safest path to follow at all times. We will endeavour to keep noise to a minimum where possible.
Additional Info
The areas highlighted in BLUE indicates the work zones. This site will be operating under footpath closures and a shoulder closure.
Businesses will be able to still access their properties, we ask that you allow extra time in case machinery is working directly outside your driveway as it can take some time to make a passage for you to enter/ exit.
KINGSLEY PLACE Cul-de-sac Asphalt Resurfacing
Status: ACTIVE
Date of Works: WEDNESDAY 17TH SEPTEMBER 2025
Type of Works: Cul-de-sac Asphalt Resurfacing
The road surface and levels may change temporarily. We ask that you please drive carefully and observe the temporary speed limits.
You may experience vibrations from the heavy machinery in use and warning beeps when the vehicles are reversing. We understand the sound can carry and we apologise in advance for this temporary inconvenience.
Additional Info
The affected area is highlighted BLUE. The cul-de-sac will be closed, however there will be a Stop/Go at Eversham Road to adjust service covers and for plant movement.
Residents will still be able to access their properties. Please speak to the Traffic Management team on site to be guided safely through the worksite and we ask you allow additional time for this.
MAUNGANUI ROAD Cobble Work
Status: COMPLETED
Date of Works: SUNDAY 7TH TO WEDNESDAY 10 SEPTEMBER 2025 - Night Works
Type of Works: COBBLE WORK
The works will include extraction of the cobblestones, smoothing out the underlaying area, and reinstalling the cobbles to enhance pedestrian safety and ensure the security of all road users.
Additional Info
Maunganui Road will be closed between Pacific Avenue and Prince Avenue. The area highlighted in BLUE indicates the work area.
Residents/Businesses will be able to still access their properties, we ask that you allow extra time in case machinery is working directly outside your driveway as it can take some time to make a passage for you to enter/ exit.
TE NGAIO ROAD Footpath Repair
Status: COMPLETED
Date of Works: MONDAY 8TH AND TUESDAY 9TH SEPTEMBER 2025
Type of Works: FOOTPATH REPAIR
Pedestrians will be shown the safest path to follow at all times. We will endeavour to keep noise to a minimum where possible.
Additional Info
The area highlighted in BLUE indicates the work zones, while the ORANGE will be operating under STOP/GO.
Residents will be able to still access their properties, we ask that you allow extra time in case machinery is working directly outside your driveway as it can take some time to make a passage for you to enter/ exit.
PORTSIDE DRIVE Asphalt Resurfacing
Status: COMPLETED
Date of Works: WEDNESDAY 3RD SEPTEMBER 2025 - Night Works
Type of Works: Asphalt Resurfacing
Please note that these works must be undertaken at night due to the traffic volumes during the day and being unable to maintain traffic access during these works.
As part of the staging for these works, you may experience a temporary road surface with level changes. Please drive carefully through the site.
Additional Info
The affected area is highlighted BLUE. The site will be operating under stop/go traffic management. Residents and businesses will still be able to access their properties if required.
Please ask our traffic management team and allow them time to arrange access.
PACIFIC AVENUE Kerb Repairs
Status: COMPLETED
Date of Works: TUESDAY 26TH AND WEDNESDAY 27TH AUGUST 2025
Type of Works: KERB REPAIR
Pedestrians will be shown the safest path to follow at all times. We will endeavour to keep noise to a minimum where possible.
Additional Info
Please note the BLUE highlights the working area. Please note that this site will be operating under a lane diversion and footpath closure. Please allow extra time when travelling through the site.
During the curing process, it’s essential that no traffic passes over the freshly poured kerb. The driveway will be open for traffic again on Thursday 28th August.
PACIFIC AVENUE Footpath Repair
Status: COMPLETED
Date of Works: TUESDAY 19TH & WEDNESDAY 20TH AUGUST 2025
Type of Works: FOOTPATH REPAIR
Pedestrians will be shown the safest path to follow at all times. We will endeavour to keep noise to a minimum where possible.
Additional Info
Please note the BLUE highlights the working areas. This site will be operating under Stop / Go.
Residents will be able to still access their properties, we ask that you allow extra time in case machinery is working directly outside your driveway as it can take some time to make a passage for you to enter/ exit.
TOTARA STREET Maintenance Repairs - Mill and Fill Repairs
Status: COMPLETED
Date of Works: WEDNESDAY 20TH AUGUST 2025 - Night Works
Type of Works: MILL & FILL PATCHES
MILL & FILL PATCHES: Removing the top layer of deteriorated pavement and relaying with asphalt.
Additional Info
The highlighted ORANGE shows the working area. The highlighted BLUE area will be closed while the work is being undertaken.
Traffic will be able to access Totara Street from Hewletts Road heading northbound only.
Businesses will still be able to access their properties if required. Please ask our traffic management team and allow them time to arrange access.
HULL ROAD Footpath Repair
Status: COMPLETED
Date of Works: MONDAY 18TH AUGUST 2025
Type of Works: FOOTPATH REPAIR
Pedestrians will be shown the safest path to follow at all times. We will endeavour to keep noise to a minimum where possible.
Additional Info
Please note the BLUE highlights the working area. This site will be operating under footpath closures and a shoulder closure.
Businesses will be able to still access their properties, we ask that you allow extra time in case machinery is working directly outside your driveway as it can take some time to make a passage for you to enter/ exit.
Read More About Our Work
-
FAQs
-
Asphalting
-
Chip Sealing
-
Stabilising
-
Footpaths